Seaford Road Level Crossing Removal - CSR Works

32696670_244309936304621_7036795287288938496_n
32911603_244309856304629_8389813605909921792_n
32834000_244309796304635_4172134452559872000_n
32693287_244309772971304_4521581306819117056_n
32760131_244309626304652_4432773275902279680_n
45152528_356446348424312_6867554312898215936_o
45213266_356446021757678_1677371525805637632_o
45179607_356446405090973_86955869220110336_o
32696670_244309936304621_7036795287288938496_n
32911603_244309856304629_8389813605909921792_n
32834000_244309796304635_4172134452559872000_n
32693287_244309772971304_4521581306819117056_n
32760131_244309626304652_4432773275902279680_n
45152528_356446348424312_6867554312898215936_o
45213266_356446021757678_1677371525805637632_o
45179607_356446405090973_86955869220110336_o

Project details

  • Name of Project: Seaford Road Level Crossing Removal - CSR
  • Client: Southern Program Alliance (SPA)
  • Date: March 2018 - September 2018
  • Location: Kananook

The BDS Civil and Construction team was asked to assist in the installation of permanent CSR and temporary signalling systems including local works from Kananook station to Eel Race Road in Seaford (approximately 5km).

Tasks successfully completed:
  • Conduit Installation
  • Pit Installation
  • ULX and URX Works
  • Deep Shield Trenching
  • Installation of Trenching Counters
  • Installation of Train stops
  • Installation of signal butt and signal HV cabinet foundations